Forward Pass Calculations in Precedence Diagram Method (PDM), determine the minimum dates at which each construction activity can be performed and, ultimately, the minimum duration of a construction project. Forward pass is a technique to move forward through network diagram to determining project duration and finding the critical path or Free Float of the project.